Progress During March 2010

  • Wall at the rear (widest part) of the building. This will be the back of the bedrooms.
  • Orshi about to insulate the cavity.
  • To the right of the front door. Stone and block cavity wall.
  • Ellie pointing.
  • Orshi brick laying
  • Marcus at the top of the final column of earth/rock just prior to the start of the last dig.
  • View of the last excavation from above. You can see the profile of the adjacent retaining wall.
  • Radon membrane down, steel ready to go in.
  • The soil pipe is for the washing machine. Bit hard to tell at this stage but this corner of the basement will be the storage room.
  • Cement mixer for the concrete pour. This section of floor slab was site mixed.
  • Last floor slab in place!