Progress During March 2012

  • First fix electrics start.
  • The curved staircase is plastered.
  • Levelled floor.
  • First underfloor heating circuit is laid in the basement.
  • Lounge underfloor heating.
  • Upstairs, getting ready for the underfloor heating.
  • Ceramic leaf for the patio planters water spouts. Modelled by the artist.
  • Router version of the underfloor heating boards.
  • Making a heat exchanger.
  • Bathroom with routed underfloor heating boards.
  • Lee the welder making corrections and additions to the stairs.
  • Painting the patio.
  • Batons in place for the insulation.
  • Bathroom sink.
  • Lee commissioning the boiler.
  • Pressure testing the underfloor heating.
  • The middle layer of the roof insulation is sheeps wool.
  • The first plasterboard to go in.