Progress During May 2010

  • Top of the internal wall for the last section of basement.
  • Ready for the last ground level floor slab to complete the basement.
  • Concrete chute in place, ready to pour.
  • The joists rest on this course so it needs to be very level.
  • String to check the joist slots are in the right places.
  • Anna tidying up mortar stains with super dangerous brick acid.
  • Joist slots
  • Precision block-work calls for a level head
  • Decorative stone panels in wall between the toblerhome and the neighbouring patio.
  • The basement is complete! This is the last ground level floor slab.
  • Celebrating the complete basement.
  • Start of the ground level bedroom wall.