Progress During November 2008
-
Insulation under the concrete section of the spiral staircase is complete.
-
-
Mortar fillet from the retaining wall to the foamglas.
-
-
Radon membrane down and taped. Rebar starting to be built.
-
-
-
-
Shuttering starts to go back in. I hadn't left enough clearance. I need 40mm. I had to remove the rebar and radon barrier and then dig down and reposition the foamglas slightly deeper. A major pain for a 30mm mis-measurement.
-
-
Shuttering all back in place.
-
-
Correct 40mm clearance this time!