Progress During September 2007

  • The excavation at the rear of the building is 2m deep.
  • Steelwork arrives on the 10th September
  • Each bundle weighs more then can be picked up by a couple of people so the steel is unloaded by just dumping it onto the street. It doesn't look like a lot of steel but this pile weighs 1.42 tonnes.
  • Priming my water level. Will explain this some other time.
  • Sand, cement and ties arrive. What is it with delivery drivers and placing things in front of doors?
  • Trial gluing with the 2 part bitumen PC56 to determine how thick I need to spread it.
  • Constructing the shuttering started on the 15th.
  • Shuttering for one base
  • Learning to tie steel
  • just look at the accurracy