Progress During September 2010

  • The windows on the Sydenham Lane side need to be bricked up as there will be a kitchen there and they are at foot level when standing up stairs.
  • Cleaning re-claimed (freecycled) Victorian bricks. These are imperial sized so will be a better match to brick up the windows on the Sydenham Lane side.
  • Preparing for the right coin.
  • Bath stone lintels going in.
  • Bath stone lintels on the Sydenham Lane side.
  • View of the ground floor taken from the bin and bike store which is at the pointy end of the building.
  • The view out of the bin and bike store.
  • Almost the last of the summer sun.
  • Connection to the gas mains.
  • With some of the hoardings down for the gas, this is my first proper view of the stone front wall. I think I'm happy with it.
  • Bin and bike store with external lintel in place.
  • This is the 18th lintel I've put in place. There are only 6 openings.
  • Gas connection.